Wire Harness RFQs: Align the Drawing, BOM, and Wire List Before Quoting
Calling an attachment “the latest” does not tell a supplier whether it matches the BOM or wire list. A useful harness RFQ identifies the revision and release status of every file in the quotation package.

When a wire-harness project reaches quotation, the problem is often not a missing drawing. It is a package that disagrees with itself: the assembly drawing is Rev C, the BOM is Rev B, and the wire list came from an earlier email. Suppliers can still return prices, but they may be pricing different builds. Comparing those numbers will not tell you much.
Set the quotation basis before sending the RFQ. Put a document number, title, revision, and issue date on each file. In the email or document index, state which files are released and which items remain open. “Final” or “latest” in a filename is not reliable, especially when purchasing, engineering, and the supplier keep separate copies.
Make clear which file controls
List the assembly drawing, BOM, wire list or pinout table, and any project inspection or test specification in one index. Include the identifier, revision, date, and status for each. If a file is still a draft, say whether it supports a budgetary estimate or forms part of the formal quotation basis. A draft should not quietly become the production definition.
The harness drawing usually describes the assembly layout, branch dimensions, and installation relationships. The BOM identifies components; the wire list defines circuit connections from connector cavity to cavity. Check that connector part numbers, wire IDs, colours, gauges, and quantities agree across all three. A connector or length change may require updates to more than one file.
Give the BOM parts a supplier can identify
“Connector,” “terminal,” or “high-temperature wire” may not be enough to price a build. If the customer specifies a part, provide its manufacturer and full part number. If substitutions are allowed, list approved alternatives and name the person who can approve one. Mark undecided components as open items and identify who will resolve them.
Wire details should map to a circuit or wire ID: conductor size, insulation or jacket requirement, colour, length, and tolerance. Do not combine an old part number, an outdated colour chart, and a new length from separate files without noting the differences. A quote is comparable only when suppliers use the same configuration.
A sample can help, but it does not replace revision control
A sample can help check fit, assembly space, and handling. Photographs can show routing inside the equipment. Neither necessarily defines pin assignments, internal connections, or permitted tolerances. If the sample differs from the drawing, state which source governs and whether the sample is for appearance, assembly reference, or a pending engineering baseline.
When engineering releases an update, do more than resend a file. Add a short change note: what changed, which parts or dimensions are affected, whether the old file is obsolete, and whether previous pricing still applies. The supplier can then confirm any cost, lead-time, or sample impact. A named customer contact should approve any substitution or deviation in writing.
Tie inspection and testing to the project documents
IPC/WHMA-A-620F is the cable and wire-harness assembly standard listed in IPC’s current catalogue. It describes materials, methods, tests, and acceptance criteria. It is not an automatic default for every order. If a project calls for it, state the revision and the applicable customer scope, then specify which records are required. Project documents still need to define the test method and acceptance values.
If the customer has not issued a test plan, do not present continuity, pull, insulation, or other tests as settled requirements in the RFQ. List the open questions and have the engineering or quality owner confirm them before they become part of the quote and acceptance criteria.
A quick check before sending the package
Before releasing the RFQ, confirm:
- The document number, revision, and release status of the drawing, BOM, wire list, and test files;
- That connector, terminal, wire, gauge, length, colour, and substitution details agree;
- That pinout, branch dimensions, orientation, and tolerances are defined in the right files;
- How samples and photographs should be used, and which source controls if they conflict with the drawing;
- The required tests, acceptance criteria, records, and approval owner;
- Who issues and approves revisions, how obsolete files are withdrawn, and whether a change requires a revised quotation.
HSC’s current catalogue includes Internal Wiring Harness, Internal High Temp Wiring Harness, and Ribbon Cable. Confirm any proposed configuration against the drawing, intended use, and project documents. Browse the Wire Harnesses category to see the current product directions.
This article provides general industry information. Specific technical requirements remain subject to the current standards and certification-body rules of the target market.
RELATED EVIDENCE
Related products and certifications
PROJECT SOURCING & RFQ
Need help confirming plug standards, certifications, or custom specs?
Share your target market, electrical ratings, cable construction, or BOM and our team will respond within 24 business hours.
Request a Project Quote